Project Description:
AYER- ROADWAY REHABILITATION ON ROUTE 2A/111 (PARK STREET AND MAIN STREET)
The proposed project involves roadway rehabilitation and installation of a traffic signal. Additional work entails sidewalk reconstruction and minor improvements to bicycle accommodations. The project limits extend from200 feet north of the Mill Street intersection to 350 feet east of the Columbia Street intersection, a distance of approximately 2,300 feet.
Location:
  • Town of Ayer
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2029
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $4,400,000.00
    Estimated Total Federal Participating Construction Cost: $4,800,000.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 115797 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: AYER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,454,400.00
    State Cost: $1,113,600.00
    Total Cost: $5,568,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/09/2018
    Project Need Form PNF Approved 04/25/2018
    Project Initiation Form PIF Entered 08/09/2018
    Project Initiation Form PIF Approved 08/09/2018
    Project Initiation Form PRC Submitted 11/19/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Management