Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BLANDFORD- RUSSELL- RESURFACING AND RELATED WORK ON I-90
Location:
  • Town of Blandford
  • Town of Russell
  • Construction Begins: Summer 2019
    Resident Engineer: Darin Aitken
    Construction Bid Price: $5,792,642.90
    District: District 1

    Contracts (1) Progress
    # 106916 -- Construction Contract
    Resurfacing and Related Work along a Section of Interstate 90 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/09/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/05/2018
    Project Initiation Form PIF Entered 09/05/2018
    Project Initiation Form PRC Submitted 09/28/2018
    Project Review Committee PRC Approved 09/28/2018
    Project Status Advertised 01/26/2019
    Project Management
    100% Design 100% Package Received 12/05/2018
    100% Design 100% Package Received 12/05/2018
    25% Design 25% Package Received 10/11/2018
    75% Design 75% Package Received 10/11/2018
    75% Design 75% Package Comments to DE 11/15/2018
    Final Design PS&E Received 12/05/2018
    Final Design PS&E Received - Resub 1 01/10/2019