Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ASHBURNHAM- ROADWAY REHABILITATION ON ROUTE 101 SOUTH
The proposed project extends from the intersection of Corey Hill Road to the Ashburnham/Gardner Town line, approximately 2 miles. The project involves roadway reclamation with minor widening to accommodate 2-11 foot travel lanes and 1-10 foot raised pedestrian/bike facility on one side of the roadway for 2,500' and 5' wide bike lanes on both sides for the remainder of the project. Sidewalks will be reconstructed where they currently exist to 5.5 foot minimum widths or wider in the case of the shared use paths. Sidewalks will be ADA/AAB compliant. The design will provide safety improvements, including a consistent typical section and bicycle accommodations along Route 101.
Location:
  • Town of Ashburnham
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: David Shedd
    Estimated Total Contract Cost: $15,780,454.22
    Estimated Total Federal Participating Construction Cost: $17,521,223.78
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: 75% Package Received (as of 04/16/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: ASHBURNHAM
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $7,118,939.20
    State Cost: $1,779,734.80
    Total Cost: $8,898,674.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/17/2018
    Project Need Form PNF Approved 07/30/2018
    Project Initiation Form PIF Entered 09/17/2018
    Project Initiation Form PIF Entered 01/10/2019
    Project Initiation Form PIF Approved 09/17/2018
    Project Initiation Form PRC Submitted 11/05/2018
    Project Initiation Form PRC Submitted 01/10/2019
    Project Review Committee PRC Tabled 12/06/2018
    Project Review Committee PRC Approved 01/10/2019
    Project Management
    25% Design 25% Package Received 04/14/2020
    25% Design 25% Package Approved 03/06/2023
    25% Design Design Public Hearing 09/14/2023
    75% Design 75% Package Received 04/16/2025