Planned Federal FY: |
2027 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
LYNN
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction; STBG+HSIP Total Cost = $45,897,600; AC schedule anticipated over 3 years
(2027-2029); Total funding in this TIP =
$35,000,000; MPO
Evaluation Score = 74.9.
|
|
Category |
FA - Hwy Safety Improvement Prgm (HSIP) |
|
Federal Cost: |
$2,700,000.00 |
State Cost: |
$300,000.00 |
Total Cost: |
$3,000,000.00 |
|
|
|
Planned Federal FY: |
2027 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
LYNN
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction; STBG+HSIP Total Cost = $45,897,600; AC schedule anticipated over 3 years
(2027-2029); Total funding in this TIP =
$35,000,000; MPO
Evaluation Score = 74.9.
|
|
Category |
FA - Surface Trans. Block Grant (STBG) |
|
Federal Cost: |
$9,600,000.00 |
State Cost: |
$2,400,000.00 |
Total Cost: |
$12,000,000.00 |
|
|
|
Planned Federal FY: |
2028 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
LYNN
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction; STBG+HSIP Total Cost = $45,897,600; AC schedule anticipated over 3 years
(2027-2029); Total funding in this TIP =
$35,000,000; MPO
Evaluation Score = 74.9.
|
|
Category |
FA - Hwy Safety Improvement Prgm (HSIP) |
|
Federal Cost: |
$4,500,000.00 |
State Cost: |
$500,000.00 |
Total Cost: |
$5,000,000.00 |
|
|
|
Planned Federal FY: |
2028 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
LYNN
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Construction; STBG+HSIP Total Cost = $45,897,600; AC schedule anticipated over 3 years
(2027-2029); Total funding in this TIP =
$35,000,000; MPO
Evaluation Score = 74.9.
|
|
Category |
FA - Surface Trans. Block Grant (STBG) |
|
Federal Cost: |
$12,000,000.00 |
State Cost: |
$3,000,000.00 |
Total Cost: |
$15,000,000.00 |
|
|
|
|