BILLERICA- INTERSECTION IMPROVEMENTS AT BOSTON ROAD (ROUTE 3A), LEXINGTON STREET AND GLAD VALLEY ROAD
Location:
  • Town of Billerica
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Kimberley Sloan
    Estimated Total Contract Cost: $4,146,430.00
    Estimated Total Federal Participating Construction Cost: $5,220,879.53
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Received (as of 08/30/2022 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,172,153.60
    State Cost: $1,043,038.40
    Total Cost: $5,215,192.00

    Planned Federal FY: 2026
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: BILLERICA
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $225,527.20
    State Cost: $56,381.80
    Total Cost: $281,909.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2018
    Project Need Form PNF Approved 09/28/2018
    Project Initiation Form PIF Entered 10/19/2018
    Project Initiation Form PIF Approved 10/19/2018
    Project Initiation Form PRC Submitted 10/19/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Management
    25% Design 25% Package Received 01/08/2020
    25% Design 25% Package Comments to DE 06/01/2020
    25% Design 25% Package Received - Resub 1 04/09/2021
    25% Design Design Public Hearing 05/24/2022
    75% Design 75% Package Received 08/30/2022