Project Description:
LAWRENCE- INTERSECTION IMPROVEMENTS AT SOUTH BROADWAY (ROUTE 28) AND MOUNT VERNON STREET
The project is located on South Broadway at the intersection with Mount Vernon Street and McKinley Avenue. Project limits along South Broadway are expected to begin approximately 50 feet south of South Street and extend to Gorham Street. Project limits along Mount Vernon Street are expected to extend approximately 100 feet west of South Broadway. Total project length is approximately 750 feet. The proposed improvements are intended to enhance safety and operations at the signalized intersection and provide improved pedestrian and bicycle accommodations. The existing antiquated traffic signal system will be replaced to meet current standards and to include McKinley Avenue, with vehicle detection, side street split phasing, various time-of-day timing plans, accessible pedestrian signals, and emergency vehicle preemption. Under the recommended alternative, an exclusive left-turn lane will be introduced on the northbound approach to facilitate protected-permissive left-turn phasing, given the high volume of northbound left-turns (33% of northbound movements). Proposed timing will be optimized to minimize vehicle stops, delays, and queues. Under the recommended alternative bicycle accommodations will consist of shared-use bicycle markings (sharrows) on South Broadway; a second alternative under consideration would provide bike lanes on South Broadway in lieu of an exclusive left-turn lane. Pedestrian accommodations will consist of reconstruction of sidewalks for ADA/AAB compliance, installation of accessible pedestrian signals, and installation of accessible curb ramps. On-street parking will be maintained where legally allowed, beyond the immediate signalized intersection. Existing granite curbing will be reset to restore a typical 6-inch reveal, with new granite curb installed where necessary to accommodate new radii. Storm drainage will be updated at the intersection to accommodate the proposed geometry; and opportunities to facilitate future separation of storm and sanitary sewer systems along South Broadway will be evaluated and incorporated if feasible. Access management measures will also be evaluated and implemented, where feasible, for adjacent commercial driveways. Lane widths will be 11-feet in both directions along South Broadway, with a 10-foot left-turn lane provided on the northbound approach under the recommended alternative. Current on-street parking will be maintained with an 8-foot wide designated parking lane under the recommended alternative and a 7-foot parking lane under the bike lane alternative. A sidewalk that varies from 8-feet to 10-feet is proposed along both sides with the installation curb extensions (“bump-outs”) at the intersection with Mount Vernon Street and McKinley Avenue to reduce pedestrian crossing distances and improve pedestrian sight lines beyond parked vehicles. West of the intersection, Mount Vernon Street will have 13-foot lanes in both directions with on-street parking maintained on both sides. The ex
Location:
  • City of Lawrence
  • Construction Begins: Spring 2021
    Resident Engineer: James Vayanos
    Construction Bid Price: $794,637.26
    District: District 4

    Contracts (1) Progress
    # 113849 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at South Broadway (Route 28) and Mount Vernon Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/01/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2018
    Project Need Form PNF Approved 08/09/2018
    Project Initiation Form PIF Entered 10/19/2018
    Project Initiation Form PIF Approved 10/19/2018
    Project Initiation Form PRC Submitted 10/19/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Status Advertised 01/16/2021
    Project Management
    100% Design 100% Package Received 06/11/2020
    100% Design 100% Package Comments to DE 07/31/2020
    25% Design 25% Package Received 04/25/2019
    25% Design 25% Package Comments to DE 07/08/2019
    25% Design Design Public Hearing 12/16/2019
    75% Design 75% Package Received 06/11/2020
    Final Design PS&E Received 09/21/2020
    Final Design PS&E Received - Resub 1 11/20/2020