Project Description:
LYNN- REHABILITATION OF ESSEX STREET
The proposed project will provide safety and operational improvements along approximately one mile of the Essex Street corridor, a minor arterial connecting Marblehead and Swampscott with downtown Lynn. The project will make incorporate enhancements to four High Crash Clusters along the Essex Street Corridor in the City of Lynn: 1) Eastern Avenue (Route 129A) at Essex Street; 2) Essex Street at Chatham Street; 3) Chestnut Street from Essex Street to Union Street, including the intersection of Essex Street at Fayette Street; and 4) Essex Street at Rockaway Street and Joyce Street. Two of these have been ranked within the Top 200 crash locations in Massachusetts: Essex Street at Rockaway Street/Joyce Street (based on 2013-2015 data); and Essex Street at Eastern Avenue (based on 2012-2014 data. The project will generally include targeted safety improvements including replacement of outdated and non-MUTCD compliant traffic signals and other traffic control devices; reconstruction of sidewalks, crosswalks, and wheelchair ramps; addition of bicycle facilities; improvements to transit stops; and roadway resurfacing.
Location:
  • City of Lynn
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2026
    Project Manager: David Shedd
    Estimated Total Contract Cost: $18,144,000.00
    Estimated Total Federal Participating Construction Cost: $18,941,000.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: LYNN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $19,698,640 (CMAQ, HSIP, STBG)
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,600,000.00
    State Cost: $400,000.00
    Total Cost: $4,000,000.00

    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: LYNN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $19,698,640 (CMAQ, HSIP, STBG)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,158,912.00
    State Cost: $1,039,728.00
    Total Cost: $5,198,640.00

    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: LYNN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $19,698,640 (CMAQ, HSIP, STBG)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $8,400,000.00
    State Cost: $2,100,000.00
    Total Cost: $10,500,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2018
    Project Need Form PNF Approved 07/23/2018
    Project Initiation Form PIF Entered 10/19/2018
    Project Initiation Form PIF Approved 09/27/2018
    Project Initiation Form PRC Submitted 10/19/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Management