Project Description:
WILMINGTON- INTERSECTION IMPROVEMENTS AT LOWELL STREET (ROUTE 129) AND WOBURN STREET
The proposed project is to construct intersection improvements at Lowell Street (Route 129) / Woburn Street to reduce vehicular congestion and peak hour delays as well as improve multi-modal safety and reduce vehicular crashes. The project would include upgrading the existing traffic signal to provide modern equipment with increased visibility for all modes of transportation. Dedicated left turn lanes are proposed on all four approaches to the intersection. An additional right turn lane is proposed on the eastbound approach of Lowell Street. Bicycle lanes will be provided on all four approaches. New or rehabilitated sidewalk, ADA/AAB accessible ramps, crosswalks and pedestrian signal equipment is proposed on all four approaches to the intersection. Curbing and drainage improvements are included. Utility poles will be relocated and/or equipment consolidated. Mill and overlay of the pavement is anticipated within the project limits - 1600 feet of Lowell Street and 1000 feet of Woburn Street. TEC conducted a Road Safety Audit (RSA) for the intersection on December 12, 2017 to determine intersection deficiencies and potential improvements. The proposed project mitigates many of the safety issues identified during the RSA.
Location:
  • Town of Wilmington
  • Construction Begins: Spring 2023
    Resident Engineer: Jared Conway
    Construction Bid Price: $5,466,188.37
    District: District 4

    Contracts (1) Progress
    # 121735 -- Construction Contract
    Intersection Improvements at Lowell Street (Route 129) and Woburn Street 63% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/22/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2018
    Project Need Form PNF Approved 10/04/2018
    Project Initiation Form PIF Entered 10/19/2018
    Project Initiation Form PIF Approved 10/19/2018
    Project Initiation Form PRC Submitted 10/19/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Status Advertised 04/01/2023
    Project Management
    100% Design 100% Package Received 08/08/2022
    100% Design 100% Package Comments to DE 09/09/2022
    25% Design 25% Package Received 06/11/2019
    25% Design 25% Package Comments to DE 09/13/2019
    25% Design Design Public Hearing 11/25/2020
    75% Design 75% Package Received 08/10/2021
    75% Design 75% Package Comments to DE 11/09/2021
    Final Design PS&E Received 12/05/2022
    Final Design PS&E to FAPRO 03/21/2023