Project Description:
LYNN- INTERSECTION IMPROVEMENTS AT TWO INTERSECTIONS ON BROADWAY
The proposed project will reconstruct approximately 0.3 miles of Broadway, from Wyoma Square to Jenness Street. The project is intended to provide safety and operational improvements at two high crash clusters; the intersections of Broadway with Euclid Avenue and with Jenness Street. The project will generally include targeted safety improvements including replacement of outdated and non-MUTCD compliant traffic signals and other traffic control devices; reconstruction of sidewalks, crosswalks, and wheelchair ramps; addition of bicycle facilities; improvements to transit stops; and roadway resurfacing. The preliminary concept design includes signalizing the stop-controlled intersection of Broadway at Jenness Street.
Location:
  • City of Lynn
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Aldo Cassano Jr.
    Construction Bid Price: $5,103,461.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4

    Contracts (3) Progress
    # 115797 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 124915 -- Construction Contract
    Intersection Improvements at Two Intersections on Broadway
    # 77889 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/06/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: LYNN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Added via STIP Action #1.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $5,842,614.60
    State Cost: $649,179.40
    Total Cost: $6,491,794.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2018
    Project Need Form PNF Approved 07/23/2018
    Project Initiation Form PIF Entered 10/19/2018
    Project Initiation Form PIF Approved 09/27/2018
    Project Initiation Form PRC Submitted 10/19/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Status Advertised 12/30/2023
    Project Management
    100% Design 100% Package Received 05/19/2023
    100% Design 100% Package Comments to DE 06/20/2023
    25% Design 25% Package Received 06/08/2020
    25% Design 25% Package Comments to DE 10/15/2020
    25% Design Design Public Hearing 12/14/2021
    75% Design 75% Package Received 12/21/2022
    75% Design 75% Package Comments to DE 01/23/2023
    Final Design PS&E Received 11/10/2023
    Final Design PS&E Received - Resub 1 12/14/2023
    Consultant Contract Process NTP Issued 06/13/2019