Project Description:
MANSFIELD- MULTIMODAL ACCOMMODATION ON SCHOOL STREET, FROM SPRING STREET TO WEST STREET
Work on this project includes roadway improvements on School Street from Spring Street to West Street (approximately 2100'). Shoulders will be constructed to accommodate bicycles and sidewalks will be included to accommodate all users. Bituminous berm will line most of the roadway and the sidewalk will be separated from the roadway by a 3' grass strip. The School Street and Spring Street intersection will be tightened up by reducing the pavement area which will slow down traffic. Willow Street will tee into Spring Street providing more separation between School Street and Willow Street. Drainage, signage and striping will be incorporated throughout the project.
Location:
  • Town of Mansfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: Aidee Cira
    Estimated Total Contract Cost: $3,692,907.00
    Estimated Total Federal Participating Construction Cost: $4,343,951.98
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Received (as of 11/20/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MANSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $5,254,715 - $4,028,461 STBG/$1,226,254 CMAQ d) EC Score 42 of 100; h) Project Proponent - Mansfield; i) Status Pre 25%
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $981,003.20
    State Cost: $245,250.80
    Total Cost: $1,226,254.00

    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MANSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $5,254,715 - $4,028,461 STBG/$1,226,254 CMAQ d) EC Score 42 of 100; h) Project Proponent - Mansfield; i) Status Pre 25%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,222,768.80
    State Cost: $805,692.20
    Total Cost: $4,028,461.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2018
    Project Need Form PNF Approved 08/07/2018
    Project Initiation Form PIF Entered 10/19/2018
    Project Initiation Form PIF Approved 10/19/2018
    Project Initiation Form PRC Submitted 10/19/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Management
    25% Design 25% Package Received 02/26/2021
    25% Design 25% Package Received - Resub 1 10/25/2022
    25% Design Design Public Hearing 04/11/2023
    75% Design 75% Package Received 11/20/2023