Project Description:
LANESBOROUGH- RESURFACING AND SIDEWALK CONSTRUCTION ON ROUTE 7
This project proposes resurfacing and related work on Route 7 in Lanesborough from the Bridge St/Prospect St intersection to about 1500 feet north of Bailey Road; a distance of 1.7 miles. The project will also include construction of a new sidewalk, by town request, from Town Hall to Bill Laston Memorial Park, about 3200 feet.
Location:
  • Town of Lanesborough
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $3,069,000.00
    Estimated Total Federal Participating Construction Cost: $3,400,000.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LANESBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $2,937,600.00
    State Cost: $734,400.00
    Total Cost: $3,672,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2018
    Project Need Form PNF Approved 06/29/2018
    Project Initiation Form PIF Entered 10/19/2018
    Project Initiation Form PIF Approved 06/29/2018
    Project Initiation Form PRC Submitted 11/26/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Management