Project Description:
NORTH ADAMS- RECONSTRUCTION OF ASHLAND STREET
Location:
  • City of North Adams
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: Herrio Lamothe
    Estimated Total Contract Cost: $8,199,932.28
    Estimated Total Federal Participating Construction Cost: $5,792,500.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: Design Public Hearing (as of 08/24/2022 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTH ADAMS
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Total Project Cost = $8,153,760; YOE = 12%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $6,523,008.00
    State Cost: $1,630,752.00
    Total Cost: $8,153,760.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/05/2018
    Project Need Form PNF Approved 10/11/2018
    Project Initiation Form PIF Entered 11/05/2018
    Project Initiation Form PIF Approved 11/05/2018
    Project Initiation Form PRC Submitted 11/26/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Management
    25% Design 25% Package Received 01/25/2021
    25% Design 25% Package Received - Resub 1 01/11/2022
    25% Design Design Public Hearing 08/24/2022