NORTH ADAMS- RECONSTRUCTION OF ASHLAND STREET
The work under this Contract consists of approximately 0.72 miles of roadway improvements on Ashland Street in North Adams from Davenport Street to Summer Street. The project expands on the City of North Adams’s pedestrian and bicycle network by providing accessible pedestrian ways and bike accommodations along Ashland Street. Bus shelter improvements, benches, and trash receptacles will also be incorporated in areas of higher pedestrian traffic. Additional improvements include storm drain and minor water system updates along the corridor.
Location:
  • City of North Adams
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: Herrio Lamothe
    Estimated Total Contract Cost: $9,281,566.70
    Estimated Total Federal Participating Construction Cost: $10,866,851.76
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 100% Package Comments to DE (as of 11/07/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTH ADAMS
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Total Project Cost = $9,387,949; YOE = 4%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $7,510,359.20
    State Cost: $1,877,589.80
    Total Cost: $9,387,949.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/05/2018
    Project Need Form PNF Approved 10/11/2018
    Project Initiation Form PIF Entered 11/05/2018
    Project Initiation Form PIF Approved 11/05/2018
    Project Initiation Form PRC Submitted 11/26/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Management
    100% Design 100% Package Received 08/03/2023
    100% Design 100% Package Comments to DE 11/07/2023
    25% Design 25% Package Received 01/25/2021
    25% Design 25% Package Received - Resub 1 01/11/2022
    25% Design Design Public Hearing 08/24/2022
    75% Design 75% Package Received 10/24/2022
    75% Design 75% Package Comments to DE 01/26/2023