Project Description:
NORTHAMPTON- DOWNTOWN COMPLETE STREETS CORRIDOR AND INTERSECTION IMPROVEMENTS ON MAIN STREET (ROUTE 9)
This is a complete street project consisting of right-of-way to right-of-way altering of Main Street (Route 9)and intersecting streets in downtown Northampton, from Market Street to Bedford Terrace. This project includes improvements to sidewalks, a new separated bike lane, installation of street furniture/tree belt, new curbing, pavement, pavement markings, crosswalks, and signage, along with adjustments at crossings and signalized intersections to be more bicycle and pedestrian friendly and to improve the functioning of intersections and the roadway.
Location:
  • City of Northampton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2025
    Project Manager: Stephanie Upson
    Estimated Total Contract Cost: $29,529,089.33
    Estimated Total Federal Participating Construction Cost: $26,314,479.38
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 75% Package Comments to DE (as of 04/17/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction (YOE $19,661,701) 75.5 TEC / 25% / STBG (A/C 2025 - $16,473,207, 2026 - $8,188,484, 2027 - $5,015,928)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $13,178,565.60
    State Cost: $3,294,641.40
    Total Cost: $16,473,207.00

    Planned Federal FY: 2026
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction (YOE $19,661,701) 75.5 TEC / 25% / STBG (A/C 2025 - $16,473,207, 2026 - $8,188,484, 2027 - $5,015,928)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $6,550,795.20
    State Cost: $1,637,698.80
    Total Cost: $8,188,494.00

    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction (YOE $19,661,701) 75.5 TEC / 25% / STBG (A/C 2025 - $16,473,207, 2026 - $8,188,484, 2027 - $5,015,928)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,012,742.40
    State Cost: $1,003,185.60
    Total Cost: $5,015,928.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/08/2018
    Project Need Form PNF Approved 11/07/2018
    Project Initiation Form PIF Entered 11/08/2018
    Project Initiation Form PIF Approved 11/08/2018
    Project Initiation Form PRC Submitted 11/08/2018
    Project Review Committee PRC Approved 05/31/2024
    Project Management
    25% Design 25% Package Received 02/02/2022
    25% Design 25% Package Comments to DE 05/11/2022
    25% Design 25% Package Approved 09/01/2023
    25% Design Design Public Hearing 04/26/2023
    75% Design 75% Package Received 03/01/2024
    75% Design 75% Package Comments to DE 04/17/2024