Project Description:
WORTHINGTON- RECONSTRUCTION & RELATED WORK ON ROUTE 143 (PHASE II), FROM PERU T.L. TO COLD STREET
The project consists of pavement rehabilitation and related work on approximately 3.9 miles of Route 143 from the Peru Town Line to Cold Street in the Town of Worthington, Massachusetts. A combination full depth reconstruction with isolated mill and overlay is proposed. Roadway widening, guardrail installation, drainage improvements, retaining wall construction and intersection improvements are included in the project.
Location:
  • Town of Worthington
  • Construction Begins: Autumn 2024
    Resident Engineer: David Reynolds
    Construction Bid Price: $16,923,464.00
    District: District 1

    Contracts (1) Progress
    # 127064 -- Construction Contract
    Reconstruction & Related Work on Route 143 (Phase II), from Peru T.L. to Cold Street

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/29/2024
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/08/2018
    Project Need Form PNF Approved 10/29/2018
    Project Initiation Form PIF Entered 11/08/2018
    Project Initiation Form PIF Approved 10/29/2018
    Project Initiation Form PRC Submitted 11/26/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Status Advertised 07/13/2024
    Project Management
    100% Design 100% Package Received 12/03/2021
    100% Design 100% Package Comments to DE 03/10/2022
    25% Design Design Public Hearing 04/07/2016
    Final Design PS&E Received 12/12/2023
    Final Design PS&E Received - Resub 1 02/22/2024
    Final Design PS&E Received - Resub 2 05/15/2024
    Final Design PS&E Received - Resub 3 06/18/2024