Project Description:
PITTSFIELD- ASHUWILLTICOOK BIKE TRAIL EXTENSION, CRANE AVENUE TO MERRILL ROAD
Project includes an approximate 2,200 linear foot extension of the Ashuwillticook Rail Trail, beginning at the Phase 1 terminus Crane Ave parking lot continuing southerly ending on the south side of Merrill Road (Route 9). This Phase II includes providing a 10' wide paved path for pedestrians, cyclists, and other non-motorized users. Improvements associated with this off-road facility include spur connections to Dalton Ave sidewalk, the "Shops at Unkamet Brook", and Merrill Road sidewalk. A HAWK signal will be provided at Route 9 to safely move users across Merrill Road. ADA ramping and railings will be included at the Dalton Avenue connection to make up elevations changes near the overpass. A trailhead is proposed at Merrill Road with a limited number of "convenient spaces" handicap accessible spaces designated only for those with disabilities and maintenance vehicles. Wayfinding signage will be included to support connections to local businesses. Improvements to Dalton Ave are limited to short segment of sidewalk, guardrail repair and trail signage. Merrill Road will have traffic signage and markings replaced as well as a short segment of milling to provide a smooth surface for users crossing.
Location:
  • City of Pittsfield
  • Construction Begins: Summer 2023
    Resident Engineer: Michael Gliwski
    Construction Bid Price: $1,705,124.56
    District: District 1

    Contracts (1) Progress
    # 122130 -- Construction Contract
    Ashuwillticook Bike Trail Extension, Crane Avenue to Merrill Road 92% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 07/10/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/09/2018
    Project Need Form PNF Approved 11/08/2018
    Project Initiation Form PIF Entered 11/09/2018
    Project Initiation Form PIF Approved 11/09/2018
    Project Initiation Form PRC Submitted 11/26/2018
    Project Review Committee PRC Approved 12/06/2018
    Project Status Advertised 05/20/2023
    Project Management
    100% Design 100% Package Received 10/07/2022
    100% Design 100% Package Comments to DE 11/07/2022
    25% Design 25% Package Received 09/18/2020
    25% Design Design Public Hearing 06/07/2021
    75% Design 75% Package Received 03/23/2022
    Final Design PS&E Received 03/28/2023
    Final Design PS&E to FAPRO 05/09/2023