Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- MILTON- BRIDGE SUPERSTRUCTURE PRESERVATION, B-16-022 = M-25-001, GRANITE AVENUE OVER NEPONSET RIVER
Location:
  • City of Boston
  • Town of Milton
  • Construction Begins: Summer 2019
    Resident Engineer: Eric Mistretta
    Construction Bid Price: $2,388,829.20
    District: District 6

    Contracts (1) Progress
    # 107472 -- Construction Contract
    Bridge Superstructure Steel Repairs and Related Work (Including Painting) Br. No. B-16-022=M-25-01 (Steel Bascule) Granite Avenue over the Neponset River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/18/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/18/2018
    Project Initiation Form PIF Entered 12/18/2018
    Project Initiation Form PRC Submitted 12/18/2018
    Project Review Committee PRC Approved 12/31/2018
    Project Status Advertised 04/13/2019
    Project Management
    Final Design PS&E Received 12/31/2018
    Final Design PS&E to FAPRO 04/09/2019