Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FALL RIVER- WESTPORT- INSTALLATION OF SIGN PANELS AND SUPPORTS AT EIGHT LOCATIONS ON I-195 AND ROUTE 24
Location:
  • City of Fall River
  • Town of Westport
  • Construction Begins: Summer 2020
    Resident Engineer: Rajat Gogoi
    Construction Bid Price: $849,976.10
    District: District 5
    Current Status: Contractor continuing with civil work for highway sign foundation excavation and installation work along Route 24 NB, Fall River. Completed foundation work on 5 overhead signs with 2 remaining foundations to be completed this month. Scheduled work hours are Monday thru Friday 8:00 PM to 5:00 AM. Various work hours depending on the corridor of work. Expect periodic lane closures and restrictions. (as of 11/12/2021)

    Contracts (1) Progress
    # 111057 -- Construction Contract
    Traffic Sign Replacement and Related Work at Various Locations on Interstate 195 and Route 24

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/27/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/20/2018
    Project Initiation Form PIF Entered 12/20/2018
    Project Initiation Form PRC Submitted 12/20/2018
    Project Review Committee PRC Approved 03/21/2019
    Project Status Advertised 03/21/2020
    Project Management
    100% Design 100% Package Received 12/23/2019
    100% Design 100% Package Comments to DE 08/28/2019
    75% Design 75% Package Received 07/11/2019
    Final Design PS&E Received 02/20/2020
    Final Design PS&E to FAPRO 03/05/2020