Project Description:
MARLBOROUGH- CLEANING AND PAINTING OF M-06-009, ROUTE 20 (LAKESIDE AVENUE) OVER INTERSTATE 495 (NB & SB)
Location:
  • City of Marlborough
  • Construction Begins: Summer 2019
    Resident Engineer: Nicholas Heath
    Construction Bid Price: $1,595,666.00
    District: District 3

    Contracts (1) Progress
    # 107785 -- Construction Contract
    Bridge Painting and Related Work (Including Structural Steel Repairs) Br. No. M-06-009 Route 20 (Lakeside Avenue) over Interstate 495 (NB & SB) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/06/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/12/2019
    Project Initiation Form PIF Entered 01/12/2019
    Project Initiation Form PRC Submitted 01/14/2019
    Project Review Committee PRC Approved 02/05/2019
    Project Status Advertised 05/18/2019
    Project Management
    Final Design PS&E Received 03/05/2019
    Final Design PS&E to FAPRO 05/10/2019