Project Description:
WRENTHAM- PUBLIC WATER LINE EXTENSION AND RESIDENTIAL CONNECTIONS ON BENNETT STREET
Location:
  • Town of Wrentham
  • Construction Begins: Summer 2020
    Resident Engineer: Sean Darling
    Construction Bid Price: $1,471,000.00
    District: District 5

    Contracts (1) Progress
    # 111121 -- Construction Contract
    Public Water Line Extension and Residential Connections on a Section of Bennett Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/10/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/15/2019
    Project Initiation Form PIF Entered 01/15/2019
    Project Initiation Form PRC Submitted 02/19/2020
    Project Review Committee PRC Approved 02/19/2020
    Project Status Advertised 04/04/2020
    Project Management
    100% Design 100% Package Received 09/12/2019
    75% Design 75% Package Received 07/05/2019
    Final Design PS&E Received 10/21/2019
    Final Design PS&E to FAPRO 03/24/2020