TAUNTON- BUILDING DEMOLITION AT MASSDOT MAINTENANCE FACILITY
Location:
  • City of Taunton
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Kevin Pavao
    Construction Bid Price: $147,250.00
    District: District 5

    Contracts (1) Progress
    # 109553 -- Construction Contract
    Demolition of 5 Buildings at the Maintenance Depot at 1050 County Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/23/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/16/2019
    Project Need Form PNF Approved 12/28/2018
    Project Initiation Form PIF Entered 01/16/2019
    Project Initiation Form PIF Approved 12/28/2018
    Project Initiation Form PRC Submitted 01/16/2019
    Project Review Committee PRC Approved 02/05/2019
    Project Status Advertised 08/31/2019
    Project Management
    75% Design 75% Package Received 04/16/2019
    Final Design PS&E Received 06/19/2019
    Final Design PS&E to FAPRO 08/19/2019