ASHBY- INTERSECTION IMPROVEMENTS AT GREENVILLE ROAD (ROUTE 31) AND TURNPIKE ROAD
The project involves intersection improvements to the intersection at Greenville Road Route 31 and Turnpike Road in Ashby. The proposed improvements will likely involve milling and resurfacing, minor geometric improvements to improve visibility and channelize turning vehicles, replacing the existing flashing beacon, adding intersection warning signage and advanced "Stop Ahead" signage and update pavement markings. As part of the design, an alternatives analysis will be performed to evaluate the feasibility of various types of traffic control including a roundabout, four-way stop or a signalized intersection. The proposed improvements will reflect the recommendations from the Road Safety Audit completed for the intersection in January 2018.
Location:
  • Town of Ashby
  • Construction Begins: Autumn 2022
    Resident Engineer: Byron Beauregard
    Construction Bid Price: $2,953,345.00
    District: District 3

    Contracts (2) Progress
    # 120080 -- Construction Contract
    Roundabout Construction and Related Work Greenville Road (Route 31) at Turnpike Road Completed
    # 77875 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/17/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/28/2019
    Project Need Form PNF Approved 01/23/2019
    Project Initiation Form PIF Entered 01/28/2019
    Project Initiation Form PIF Approved 01/28/2019
    Project Initiation Form PRC Submitted 01/29/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Status Advertised 08/27/2022
    Project Management
    100% Design 100% Package Received 04/14/2022
    100% Design 100% Package Comments to DE 05/06/2022
    25% Design 25% Package Received 07/30/2020
    25% Design 25% Package Comments to DE 10/28/2020
    25% Design Design Public Hearing 04/12/2021
    75% Design 75% Package Received 07/20/2021
    Final Design PS&E Received 07/15/2022
    Final Design PS&E Received - Resub 1 08/09/2022