NORTH ADAMS- WILLIAMSTOWN- MOHAWK BIKE & PEDESTRIAN TRAIL CONSTRUCTION (PHASE II)
Location:
  • City of North Adams
  • Town of Williamstown
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Mark Moore
    Estimated Total Contract Cost: $8,105,200.00
    Estimated Total Federal Participating Construction Cost: $8,500,000.00
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/04/2019
    Project Initiation Form PIF Entered 02/04/2019
    Project Initiation Form PRC Submitted 09/20/2019
    Project Review Committee PRC Approved 10/01/2019
    Project Management