Project Description:
BOSTON- NEWTON- WESTON- BRIDGE MAINTENANCE OF 4 BRIDGES: B-16-216, N-12-013, N-12-019 & W-29-017
Location:
Construction Begins: Spring 2020
Resident Engineer: Gene Lee
Construction Bid Price: $3,290,637.50
District: District 6

Contracts (1) Progress
# 110461 -- Construction Contract
Bridge Deck, Joint and Substructure Repairs and Related Work on 4 Bridges Br. Nos. B-16-216, N-12-013, N-12-019 & W-29-017 Completed

Bridges

Contract Dates
Notice to Proceed: 06/10/2020
Contract Information
Project Designer: In-House Boston
Funding Source: Maintenance
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 02/06/2019
Project Initiation Form PIF Entered 02/06/2019
Project Initiation Form PRC Submitted 05/01/2019
Project Review Committee PRC Approved 05/06/2019
Project Status Advertised 12/21/2019
Project Management
Final Design PS&E Received 10/01/2019
Final Design PS&E Received - Resub 1 11/15/2019
Final Design PS&E Received - Resub 2 11/29/2019
Final Design PS&E Received - Resub 3 12/10/2019