DISTRICT 6- SCHEDULED & EMERGENCY REPAIR & MAINTENANCE OF HVAC SYSTEMS VARIOUS LOCATIONS
Location:
Construction Begins: Autumn 2021
Resident Engineer: Daniel Mullaly
Construction Bid Price: $120,180.00
District: District 6

Contracts (1) Progress
# 116348 -- Construction Contract
Scheduled and Emergency HVAC System Repairs and Improvements at Various Locations (Re-Advertised Project) 51% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/10/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/06/2019
    Project Initiation Form PIF Entered 02/06/2019
    Project Initiation Form PRC Submitted 05/01/2019
    Project Review Committee PRC Approved 05/06/2019
    Project Status Advertised 10/10/2020
    Project Status Advertised 09/18/2021
    Project Management
    100% Design 100% Package Received 06/24/2020
    Final Design PS&E Received 08/11/2021
    Final Design PS&E to FAPRO 09/22/2020
    Final Design PS&E to FAPRO 08/23/2021