Project Description:
BOSTON- WATER QUALITY CONTROL STRUCTURES (WQCS) CLEAN OUT & REPAIR IN I-90 & I-93 TUNNELS
Location:
  • City of Boston
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Nicholas Renaud
    Construction Bid Price: $491,506.57
    District: District 6

    Contracts (1) Progress
    # 113523 -- Construction Contract
    Scheduled and Emergency Cleaning, Inspection, and Repairs of Water Quality Control Structures (WQCS) in the I-90 & I-93 Tunnels Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/01/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/06/2019
    Project Initiation Form PIF Entered 02/06/2019
    Project Initiation Form PRC Submitted 05/01/2019
    Project Review Committee PRC Approved 05/06/2019
    Project Status Advertised 11/21/2020
    Project Management
    100% Design 100% Package Received 10/30/2020
    Final Design PS&E Received 11/02/2020
    Final Design PS&E to FAPRO 11/03/2020