| Project Description: |
MEDFIELD- MILLIS- BRIDGE PRESERVATION, M-11-002, WEST STREET OVER THE CHARLES RIVER & M-11-003, STATE 109 (MAIN STREET) OVER THE CHARLES RIVER
|
| Location: |
|
| Construction Begins: | Summer 2020 |
| Resident Engineer: | Nicholas Heath![]() |
| Construction Bid Price: | $2,396,914.00 |
| District: | District 3 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||