Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- TUNNEL LIGHTING REPLACEMENT FOR I-93 (NB/SB) RAMPS (CRC 17G)
Project includes furnishing and installing new LED tunnel luminaires in the I-93 (NB/SB) Ramp Tunnels. Work includes upgrading electrical, control and structural systems associated with the new tunnel lighting system.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2023/2024
    Project Manager: Hema P Bhatt
    Estimated Total Contract Cost: $54,007,577.08
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: Peer Review Comments to DE (as of 08/24/2023 )

    Contracts (1) Progress
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/22/2019
    Project Initiation Form PIF Received 02/22/2019
    Project Initiation Form PIF Entered 02/22/2019
    Project Initiation Form PIF Approved 04/30/2019
    Project Initiation Form PRC Submitted 04/30/2019
    Project Review Committee PRC Approved 05/06/2019
    Project Management
    100% Design 100% Package Received 05/13/2022
    100% Design 100% Package Comments to DE 06/21/2022
    25% Design 25% Package Received 09/18/2020
    25% Design 25% Package Comments to DE 11/23/2020
    75% Design 75% Package Received 10/13/2021
    75% Design 75% Package Comments to DE 01/25/2022
    Final Design PS&E Received 07/19/2023
    Final Design PS&E to Peer Reviewer 07/19/2023
    Final Design Peer Review Comments to DE 08/24/2023