Project Description:
BOSTON- TUNNEL LIGHTING REPLACEMENT FOR I-93 (NB/SB) RAMPS (CRC 17G)
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2022/2023
    Project Manager: John Czach
    Estimated Total Contract Cost: $42,765,358.43
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 25% Package Comments to DE (as of 11/23/2020 )

    Contracts (1) Progress
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/22/2019
    Project Initiation Form PIF Received 02/22/2019
    Project Initiation Form PIF Entered 02/22/2019
    Project Initiation Form PIF Approved 04/30/2019
    Project Initiation Form PRC Submitted 04/30/2019
    Project Review Committee PRC Approved 05/06/2019
    Project Management
    25% Design 25% Package Received 09/18/2020
    25% Design 25% Package Comments to DE 11/23/2020