Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORWOOD- CONCRETE MEDIAN BARRIER REPLACEMENT ON ROUTE 1
The purpose of this project is to replace the existing deteriorated concrete median barrier on Route 1 between Summer Street and Morse Street.
Location:
  • Town of Norwood
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Sean Darling
    Construction Bid Price: $1,051,195.00
    District: District 5

    Contracts (1) Progress
    # 109295 -- Construction Contract
    Concrete Median Barrier Replacement and Related Work along a Section of Route 1 (Providence Highway) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/14/2020
    Contract Information
    Project Designer: In-House Boston
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/26/2019
    Project Need Form PNF Approved 02/20/2019
    Project Initiation Form PIF Entered 02/26/2019
    Project Initiation Form PIF Approved 02/25/2019
    Project Initiation Form PRC Submitted 02/26/2019
    Project Review Committee PRC Approved 03/06/2019
    Project Status Advertised 08/10/2019
    Project Management
    100% Design 100% Package Received 07/12/2019
    25% Design 25% Package Received 06/14/2019
    75% Design 75% Package Received 06/14/2019
    75% Design 75% Package Comments to DE 07/01/2019
    Final Design PS&E Received 07/12/2019
    Final Design PS&E Received - Resub 1 07/26/2019