KINGSTON- SYSTEMATIC BRIDGE PRESERVATION, K-01-011 (AGD), ROUTE 3 OVER JONES RIVER
Location:
  • Town of Kingston
  • Construction Begins: Spring 2020
    Resident Engineer: Peter Benkart
    Construction Bid Price: $2,797,400.00
    District: District 5

    Contracts (1) Progress
    # 110042 -- Construction Contract
    Bridge Repairs and Related Work Br. No. K-01-011 (Concrete) Route 3 (Pilgrims Highway) over Jones River Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/04/2020
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/26/2019
    Project Initiation Form PIF Entered 02/26/2019
    Project Initiation Form PRC Submitted 02/26/2019
    Project Review Committee PRC Approved 03/04/2019
    Project Status Advertised 11/02/2019
    Project Management
    75% Design 75% Package Received 05/21/2019
    75% Design 75% Package Comments to DE 07/18/2019
    Final Design PS&E Received 07/26/2019
    Final Design PS&E Received - Resub 1 08/26/2019
    Final Design PS&E Received - Resub 2 09/27/2019
    Final Design PS&E Received - Resub 3 10/21/2019