Project Description:
DISTRICT 1- ADA RETROFITS AT VARIOUS LOCATIONS
The work to be done under this Contract consists of pedestrian curb ramp and sidewalk construction, repairs and upgrades in 10 Municipalities. Work shall include, but is not limited to, construction or reconstruction of cement concrete pedestrian curb ramps, cement concrete sidewalks and bituminous concrete sidewalks, removing and resetting, or replacing, curb and transition curb, drainage alterations as needed, traffic control signal upgrades as needed, and repairing of roadway cuts required to perform work. The Contractor shall prepare an appropriate Pedestrian Management Plan and Traffic Management Plan, for each location, in compliance with current MassDOT and ADA guidelines, subject to approval of the Engineer. All work shall be completed within the tolerances established in the Construction Standard Details. All work done under this contract shall be located within the State Highway Layout, City/Town Layout and the easements show on the Plans. Work shall be performed from the roadway shoulder to the maximum extent practical. MassDOT has recognized pedestrian curb ramp locations in the following cities and towns; Chester, Dalton, Great Barrington, Lee, North Adams, Otis, Pittsfield, Russell, Williamsburg and Williamstown.
Location:
Design Responsibility: Consultant
Right of Way Responsibility: MassDOT
Construction Begins: Summer 2024
Project Manager: Greg Frazier
Estimated Total Contract Cost: $3,459,036.60
Estimated Total Federal Participating Construction Cost: N/A
District: District 1
Current Status: This project has been advertised for construction bids. (as of 03/30/2024 )

Contracts (2) Progress
# 115745 -- Design -- Services
Statewide - Master Service Agreement for design and review services. Final
# 77846 -- Design -- Hwy Eng Open End
Master Service Agreement for statewide design and review services. Final

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/08/2019
    Project Need Form PNF Approved 03/08/2019
    Project Initiation Form PIF Entered 03/08/2019
    Project Initiation Form PIF Approved 03/08/2019
    Project Initiation Form PRC Submitted 03/11/2019
    Project Review Committee PRC Approved 03/13/2019
    Project Status Advertised 03/30/2024
    Project Management
    100% Design 100% Package Received 07/14/2022
    100% Design 100% Package Comments to DE 10/13/2022
    100% Design 100% Package Received - Resub 1 03/17/2023
    25% Design 25% Package Received 10/15/2021
    25% Design Design Public Hearing 05/04/2022
    75% Design 75% Package Received 07/14/2022
    Final Design PS&E Received 01/08/2024
    Final Design PS&E Received - Resub 1 02/12/2024
    Final Design PS&E Received - Resub 2 03/08/2024
    Final Design PS&E Received - Resub 3 03/22/2024