Project Description:
WENHAM- SAFETY IMPROVEMENTS ON ROUTE 1A
The work to be done under this contract consists of roadway and intersection improvements along 0.265 miles of Main Street (Route 1A) through the Town of Wenham’s downtown corridor and the reconstruction of three (3) major intersections: Cherry Street, Monument Street, and Arbor Street/Friend Court. The roadway improvements along Main Street include, but are not limited to milling and overlaying existing pavement with new bituminous concrete pavement, reconstructing ADA compliant hot mix asphalt sidewalks and cement concrete wheelchair ramps, installing new granite curb, drainage adjustments, and installing new pavement marking and signing. Intersection improvements include the installation of two (2) new traffic signal systems (including mast arms and foundations) at the intersections of Main Street with Cherry Street and Main Street with Arbor Street/Friend Court. The two (2) intersection signal systems are to operate in coordination via GPS communication, and the traffic signal equipment shall include emergency vehicle preemption.
Location:
  • Town of Wenham
  • Design Responsibility: Consultant
    Construction Begins: Autumn 2026
    Project Manager: Dongke Yu
    Estimated Total Contract Cost: $4,936,125.30
    Estimated Total Federal Participating Construction Cost: $6,084,017.60
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 100% Package Received (as of 10/17/2025 )

    Contracts (1) Progress
    # 101631 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: WENHAM
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $4,447,630.80
    State Cost: $494,181.20
    Total Cost: $4,941,812.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/08/2019
    Project Need Form PNF Approved 03/08/2019
    Project Initiation Form PIF Entered 03/08/2019
    Project Initiation Form PIF Approved 03/08/2019
    Project Initiation Form PRC Submitted 03/11/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management
    100% Design 100% Package Received 10/17/2025
    25% Design 25% Package Received 12/21/2020
    25% Design 25% Package Comments to DE 03/19/2021
    25% Design 25% Package Approved 09/10/2021
    25% Design Design Public Hearing 09/08/2022
    75% Design 75% Package Received 01/31/2024
    75% Design 75% Package Received 02/08/2024