ERVING- RESURFACING AND RELATED WORK ON ROUTE 2
This project involves resurfacing and related work on a portion of Route 2 in Erving, from mile marker 60.25 to 63.9 for a total of 3.65 miles.
Location:
  • Town of Erving
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Victor LaMountain
    Construction Bid Price: $2,297,180.36
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2

    Contracts (1) Progress
    # 124527 -- Construction Contract
    Resurfacing and Related Work on Route 2 2% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/26/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: ERVING
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $1,825,866.40
    State Cost: $456,466.60
    Total Cost: $2,282,333.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/11/2019
    Project Need Form PNF Approved 03/08/2019
    Project Initiation Form PIF Entered 03/11/2019
    Project Initiation Form PIF Approved 03/11/2019
    Project Initiation Form PRC Submitted 03/11/2019
    Project Review Committee PRC Approved 03/22/2019
    Project Status Advertised 11/04/2023
    Project Management
    25% Design 25% Package Received 04/14/2023
    75% Design 75% Package Received 04/14/2023
    75% Design 75% Package Comments to DE 05/16/2023
    Final Design PS&E Received 06/22/2023
    Final Design PS&E to FAPRO 10/20/2023