Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
RANDOLPH- RESURFACING AND RELATED WORK ON ROUTE 28
This project will provide no significant expansion of bike/pedestrian facilities and is being advanced as a pavement preservation project. If needed, accessible pedestrian ramps should be provided at existing sidewalk infrastructure, existing sidewalks should be repaired if necessary, and cross-sectional distribution should be investigated through pavement marking changes for crosswalks/bicycle accommodations.
Location:
  • Town of Randolph
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Hector Tineo
    Estimated Total Contract Cost: $6,706,300.00
    Estimated Total Federal Participating Construction Cost: $6,917,670.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: RANDOLPH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $7,194,377 (NHPP)
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,755,501.60
    State Cost: $1,438,875.40
    Total Cost: $7,194,377.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/11/2019
    Project Need Form PNF Approved 03/11/2019
    Project Initiation Form PIF Entered 03/11/2019
    Project Initiation Form PIF Approved 03/11/2019
    Project Initiation Form PRC Submitted 03/11/2019
    Project Review Committee PRC Approved 03/22/2019
    Project Management