Project Description: |
RANDOLPH- RESURFACING AND RELATED WORK ON ROUTE 28
This project will provide no significant expansion of bike/pedestrian facilities and is being advanced as a pavement preservation project. If needed, accessible pedestrian ramps should be provided at existing sidewalk infrastructure, existing sidewalks should be repaired if necessary, and cross-sectional distribution should be investigated through pavement marking changes for crosswalks/bicycle accommodations.
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2026 |
Project Manager: | Koby J Lemrise![]() |
Estimated Total Contract Cost: | $5,997,815.00 |
Estimated Total Federal Participating Construction Cost: | $6,321,315.00 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
District: | District 6 |
Current Status: | 25% Package Comments to DE (as of 03/27/2025 ) |
|
Bridges |
|
|
|