Project 609400
(Click here for a glossary of terms)
Project Description:
WORCESTER- RESURFACING AND RELATED WORK ON I-290
Location:
City of Worcester
Construction Begins:
Summer 2020
Resident Engineer:
Klodian Polisi
Construction Bid Price:
$8,682,544.91
District:
District 3
Contracts
(1)
Progress
# 111029 -- Construction Contract
Resurfacing and Related Work on Sections of I-190 & I-290
Completed
Bridges
- none -
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Contract Dates
Notice to Proceed:
07/01/2020
Contract Information
Project Designer:
In-House Boston
Funding Source:
Interstate Maintenance
Construction Progress
Milestone Details
TIP/Funding
Project Issues
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
Construction Progress
Milestone Details
TIP/Funding
Project Issues
TIP Lines for
2025 - 2029
No TIP Data Available For This Project
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Project Task Information
Project Status
Project Need Form
PNF Entered
03/11/2019
Project Need Form
PNF Approved
03/11/2019
Project Initiation Form
PIF Entered
03/11/2019
Project Initiation Form
PIF Approved
03/11/2019
Project Initiation Form
PRC Submitted
03/11/2019
Project Review Committee
PRC Approved
03/21/2019
Project Status
Advertised
03/14/2020
Project Management
100% Design
100% Package Received
02/05/2020
25% Design
25% Package Received
11/01/2019
75% Design
75% Package Received
11/01/2019
75% Design
75% Package Comments to DE
12/05/2019
Final Design
PS&E Received
02/05/2020
Final Design
PS&E to FAPRO
03/02/2020