Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEW ASHFORD- RESURFACING AND RELATED WORK ON ROUTE 7
Location:
  • Town of New Ashford
  • Construction Begins: Autumn 2019
    Resident Engineer: David Reynolds
    Construction Bid Price: $2,982,845.00
    District: District 1

    Contracts (1) Progress
    # 108590 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 7 (New Ashford Road) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/27/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/11/2019
    Project Initiation Form PIF Entered 03/11/2019
    Project Initiation Form PRC Submitted 03/15/2019
    Project Review Committee PRC Approved 03/20/2019
    Project Status Advertised 07/06/2019
    Project Management
    100% Design 100% Package Received 05/03/2019
    Final Design PS&E Received 05/03/2019
    Final Design PS&E to FAPRO 07/01/2019