Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- STEEL SUPERSTRUCTURE CLEANING (FULL REMOVAL) AND PAINTING OF 5 BRIDGES
Location:
Construction Begins: Autumn 2019
Resident Engineer: John Wagner
Construction Bid Price: $5,849,315.50
District: District 6

Contracts (1) Progress
# 108589 -- Construction Contract
Bridge Painting and Repairs at 5 Locations Completed

Bridges

Contract Dates
Notice to Proceed: 11/22/2019
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 03/12/2019
Project Initiation Form PIF Entered 03/12/2019
Project Initiation Form PRC Submitted 03/12/2019
Project Review Committee PRC Approved 03/20/2019
Project Status Advertised 07/06/2019
Project Management
Final Design PS&E Received 05/17/2019
Final Design PS&E Received - Resub 1 06/12/2019