Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SPRINGFIELD- BRIDGE REPLACEMENT, S-24-016, ARMORY STREET OVER CSX MAINLINE & S-24-026, ARMORY STREET OVER ABANDONED CSX
Location:
  • City of Springfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Anthony Christakis
    Estimated Total Contract Cost: $34,829,809.85
    Estimated Total Federal Participating Construction Cost: $36,897,333.03
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: Design Public Hearing (as of 02/01/2022 )

    Contracts (1) Progress
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $30,698,580.80
    State Cost: $7,674,645.20
    Total Cost: $38,373,226.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/14/2019
    Project Need Form PNF Approved 03/14/2019
    Project Initiation Form PIF Entered 03/14/2019
    Project Initiation Form PIF Approved 03/14/2019
    Project Initiation Form PRC Submitted 03/14/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management
    25% Design 25% Package Received 02/26/2021
    25% Design Design Public Hearing 02/01/2022