Project Description:
BROCKTON- INTERSECTION IMPROVEMENTS AND RELATED WORK AT CENTRE STREET (ROUTE 123), CARY STREET AND LYMAN STREET
The project proposes to address multimodal safety and access management at the Centre Street (Route 123)/Lyman Street/Cary Street intersection. Proposed work includes reconstructed traffic signals and sidewalks, in addition to upgrading pavement markings, signage, curbing, street lighting and drainage if necessary. Consideration is also being given to performing some geometric improvements to improve corner radii to better accommodate right turning trucks. Also, constructing new exclusive left turn lanes to process more traffic and improve vehicular safety will be considered. In addition, consideration will be given to eliminating some curb cuts very close to the intersection for purposes of improving access management. Finally, consideration of constructing a turnout at the bus stop on Lyman Street is proposed along with installing emergency vehicle pre-emption within the reconstructed signals to reduce hazards associated with moving emergency vehicles safely through the intersection.
Location:
  • City of Brockton
  • Design Responsibility: Consultant
    Construction Begins: Winter 2024/2025
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $2,646,355.42
    Estimated Total Federal Participating Construction Cost: $3,379,839.60
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 09/14/2024 )

    Contracts (1) Progress
    # 77852 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/14/2019
    Project Need Form PNF Approved 03/13/2019
    Project Initiation Form PIF Entered 03/14/2019
    Project Initiation Form PIF Approved 03/13/2019
    Project Initiation Form PRC Submitted 03/14/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Status Advertised 09/14/2024
    Project Management
    100% Design 100% Package Received 03/13/2023
    100% Design 100% Package Comments to DE 04/14/2023
    25% Design 25% Package Received 07/17/2020
    25% Design 25% Package Comments to DE 10/19/2020
    25% Design 25% Package Received - Resub 1 07/09/2021
    25% Design Design Public Hearing 04/26/2022
    75% Design 75% Package Received 03/13/2023
    Final Design PS&E Received 09/27/2023
    Final Design PS&E Received - Resub 1 02/07/2024
    Final Design PS&E Received - Resub 2 03/13/2024
    Final Design PS&E Received - Resub 3 08/13/2024