Project Description:
FITCHBURG- TWIN CITIES RAIL TRAIL CONSTRUCTION (PHASE II)
This project is to provide safer and improved transportation access for bicycle users and pedestrians between the Cities of Leominster and Fitchburg and to provide a safe connection to the MART Intermodal Transportation Center in downtown Fitchburg. As envisioned, this regional trail will connect areas of cultural, economic, social, and natural significance along the multi community corridor and provide a non-motorized transportation and recreational alternative for people of all ages and abilities. Phase 2 of the TCRT project will complete the trail in Fitchburg, by connecting the end of the current trail constructed under Phase 1 at 4th Street and continuing to the multi-modal station in downtown Fitchburg. The connection includes an on-road section along Railroad Street to approximately 1st Street, where the trail will climb a retained earth structure leading to a bridge over the MBTA Commuter Line railroad tracks, across property owned by Unitil, across the North Nashua River, and over private property to the MART property on an elevated structure. Related work includes installation of signage, pavement markings and bike path amenities.
Location:
  • City of Fitchburg
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2024
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $26,750,887.30
    Estimated Total Federal Participating Construction Cost: $27,787,472.18
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 08/31/2024 )

    Contracts (3) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: FITCHBURG
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC $27,981,128 using CMAQ ($1,000,000 in 2024, $9,583,505 in 2025, 14,000,000 in 2026)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $10,377,993.60
    State Cost: $2,594,498.40
    Total Cost: $12,972,492.00

    Planned Federal FY: 2026
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: FITCHBURG
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC $27,981,128 using CMAQ ($1,000,000 in 2024, $9,583,505 in 2025, 14,000,000 in 2026)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $11,200,000.00
    State Cost: $2,800,000.00
    Total Cost: $14,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/14/2019
    Project Need Form PNF Approved 03/14/2019
    Project Initiation Form PIF Entered 03/14/2019
    Project Initiation Form PIF Approved 03/14/2019
    Project Initiation Form PRC Submitted 03/18/2019
    Project Review Committee PRC Approved 03/21/2019
    Project Status Advertised 08/31/2024
    Project Management
    100% Design 100% Package Received 11/10/2023
    100% Design 100% Package Comments to DE 01/10/2024
    25% Design 25% Package Received 12/20/2019
    25% Design 25% Package Comments to DE 03/03/2020
    25% Design 25% Package Received - Resub 1 09/23/2022
    25% Design Design Public Hearing 04/13/2023
    75% Design 75% Package Received 07/14/2023
    75% Design 75% Package Comments to DE 09/06/2023
    Final Design PS&E Received 03/28/2024
    Final Design PS&E Received - Resub 1 06/17/2024
    Final Design PS&E Received - Resub 2 07/22/2024
    Consultant Contract Process NTP Issued 03/05/2022