Project Description:
MONTAGUE- BRIDGE REPLACEMENT, M-28-026, SOUTH STREET OVER SAWMILL RIVER
The purpose of this project is to replace the entire bridge carrying South Street over the Sawmill River. The project involves minor improvements to the river channel and riverbed. There are no utilities impacted by the project.
Location:
  • Town of Montague
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2024
    Project Manager: Christopher I Cameron
    Estimated Total Contract Cost: $3,237,881.00
    Estimated Total Federal Participating Construction Cost: $3,522,872.90
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: Final Package to FAPRO (as of 03/18/2024 )

    Contracts (1) Progress
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: MONTAGUE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Project decreased from $4,261,955 to $3,432,962 via STIP Action 3.
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $2,746,369.60
    State Cost: $686,592.40
    Total Cost: $3,432,962.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/18/2019
    Project Need Form PNF Approved 03/18/2019
    Project Initiation Form PIF Entered 03/18/2019
    Project Initiation Form PIF Approved 03/18/2019
    Project Initiation Form PRC Submitted 03/18/2019
    Project Review Committee PRC Approved 03/22/2019
    Project Management
    100% Design 100% Package Received 10/20/2023
    100% Design 100% Package Comments to DE 11/22/2023
    25% Design 25% Package Received 08/03/2022
    25% Design 25% Package Comments to DE 09/14/2022
    25% Design Design Public Hearing 01/24/2023
    75% Design 75% Package Received 05/23/2023
    75% Design 75% Package Comments to DE 06/30/2023
    Final Design PS&E Received 01/19/2024
    Final Design PS&E to FAPRO 03/18/2024
    Final Design PS&E Received - Resub 1 02/29/2024
    Final Design PS&E Received - Resub 2 03/12/2024