Project Description:
LANESBOROUGH- BRIDGE REPLACEMENT, L-03-010, BRIDGE STREET OVER TOWN BROOK
Location:
  • Town of Lanesborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2024/2025
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $2,005,592.63
    Estimated Total Federal Participating Construction Cost: $2,150,457.48
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 25% Package Received (as of 06/14/2021 )

    Contracts (1) Progress
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LANESBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $1,597,160.00
    State Cost: $399,290.00
    Total Cost: $1,996,450.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2019
    Project Initiation Form PIF Entered 03/20/2019
    Project Initiation Form PRC Submitted 04/02/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management
    25% Design 25% Package Received 06/14/2021