Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LANESBOROUGH- BRIDGE REPLACEMENT, L-03-010, BRIDGE STREET OVER TOWN BROOK
Location:
  • Town of Lanesborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2024/2025
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $3,733,050.35
    Estimated Total Federal Participating Construction Cost: $4,085,946.82
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: PS&E Received - Resub 2 (as of 03/14/2024 )

    Contracts (1) Progress
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LANESBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $2,211,174.40
    State Cost: $552,793.60
    Total Cost: $2,763,968.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2019
    Project Initiation Form PIF Entered 03/20/2019
    Project Initiation Form PRC Submitted 04/02/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management
    100% Design 100% Package Received 08/11/2022
    100% Design 100% Package Received - Resub 1 06/26/2023
    25% Design 25% Package Received 06/14/2021
    25% Design 25% Package Approved 02/24/2022
    25% Design Design Public Hearing 01/05/2022
    75% Design 75% Package Received 03/08/2022
    Final Design PS&E Received 10/30/2023
    Final Design PS&E Received - Resub 1 01/10/2024
    Final Design PS&E Received - Resub 2 03/14/2024