LANESBOROUGH- BRIDGE REPLACEMENT, L-03-010, BRIDGE STREET OVER TOWN BROOK
Location:
  • Town of Lanesborough
  • Construction Begins: Winter 2024/2025
    Resident Engineer: Michael Wall
    Construction Bid Price: $2,879,143.75
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1

    Contracts (2) Progress
    # 128616 -- Construction Contract
    Bridge Replacement, L-03-010, Bridge Street over Town Brook 4% Complete
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/27/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LANESBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,279,535.20
    State Cost: $819,883.80
    Total Cost: $4,099,419.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/20/2019
    Project Initiation Form PIF Entered 03/20/2019
    Project Initiation Form PRC Submitted 04/02/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Status Advertised 11/02/2024
    Project Management
    100% Design 100% Package Received 08/11/2022
    100% Design 100% Package Received - Resub 1 06/26/2023
    25% Design 25% Package Received 06/14/2021
    25% Design 25% Package Approved 02/24/2022
    25% Design Design Public Hearing 01/05/2022
    75% Design 75% Package Received 03/08/2022
    Final Design PS&E Received 10/30/2023
    Final Design PS&E Received - Resub 1 01/10/2024
    Final Design PS&E Received - Resub 2 03/14/2024