Project Description: |
GREAT BARRINGTON- BRIDGE REPLACEMENT, G-11-014, STATE ROAD (ROUTES 7/23) OVER THE HOUSATONIC RIVER
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2027 |
Project Manager: | Janhavi Limaye![]() |
Estimated Total Contract Cost: | $17,319,251.15 |
Estimated Total Federal Participating Construction Cost: | $18,379,573.60 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization. |
District: | District 1 |
Current Status: | 25% Package Received (as of 04/18/2025 ) |
|
Bridges
|
|
|
|