| Project Description:
|
ATTLEBORO- NORTH ATTLEBOROUGH- MEDIAN CABLE BARRIER INSTALLATION ON I-95
|
| Location:
|
City of Attleboro
Town of North Attleborough
|
| Construction Begins:
|
Autumn 2023 |
| Resident Engineer:
|
Eric Borman |
| Construction Bid Price:
|
$1,691,112.75 |
| District:
|
District 5 |
| Current Status:
|
DFC: Cable guard rail: Repairs and reflectors: Complete. MON: Loam and Seed: Complete. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Scheduled work hours are Monday through Friday, 7:00AM to 3:30PM. (as of 04/27/2026) |
| Additional Info:
|
I-95 single lane taking after 9:00 AM with traffic pickup by 2:30 PM. (as of 04/27/2026) |