Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ATTLEBORO- NORTH ATTLEBOROUGH- MEDIAN CABLE BARRIER INSTALLATION ON I-95
Location:
  • City of Attleboro
  • Town of North Attleborough
  • Construction Begins: Autumn 2023
    Resident Engineer: Eric Borman
    Construction Bid Price: $1,691,112.75
    District: District 5
    Current Status: MON installing erosion control equipment I-95. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM.. (as of 05/14/2025)
    Additional Info: I-95 single lane taking after 9:00 AM with traffic pickup by 2:30 PM. (as of 05/14/2025)

    Contracts (2) Progress
    # 123957 -- Construction Contract
    Median Cable Barrier Installation on I-95
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/30/2023
    Contract Information
    Project Designer:
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    MON installing erosion control equipment I-95. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM..
    Additional Info
    I-95 single lane taking after 9:00 AM with traffic pickup by 2:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2019
    Project Need Form PNF Approved 03/21/2019
    Project Initiation Form PIF Entered 03/21/2019
    Project Initiation Form PIF Approved 03/21/2019
    Project Initiation Form PRC Submitted 03/21/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Status Advertised 09/02/2023
    Project Management
    100% Design 100% Package Received 06/09/2023
    25% Design 25% Package Received 04/14/2022
    75% Design 75% Package Received 04/14/2022
    Final Design PS&E Received 06/09/2023
    Final Design PS&E Received - Resub 1 07/28/2023