Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
PLYMPTON- BRIDGE REPLACEMENT, P-14-001 (445), WINNETUXET ROAD OVER WINNETUXET RIVER
The intent of the design is to match existing dimensions, and to replace the bridge in-kind with a timber bridge. Widening the bridge and roadway or deviating significantly from existing conditions would result in impacts to wetlands and water, permitting requirements, ROW, and increasing the limits and costs of work.
Location:
  • Town of Plympton
  • Construction Begins: Autumn 2024
    Resident Engineer: Trevor O'Bryan
    Construction Bid Price: $1,830,655.00
    District: District 5
    Current Status: Current Operations: Demolition complete. Sheet Piling complete. Drilled shaft installation to begin 3/31/25 Future Operations: Abutment cap forming and Rebar. Drainage & full depth road excavation in the coming weeks. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/07/2025)
    Additional Info: Winnetuxet Road is currently closed to through traffic. Motorist should follow the local detour that is in place for Parsonage Road and Elm Street. (as of 04/07/2025)

    Contracts (2) Progress
    # 126585 -- Construction Contract
    Bridge Replacement, P-14-001 (445), Winnetuxet Road over Winnetuxet River 15% Complete
    # 77845 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/08/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2019
    Project Initiation Form PIF Entered 03/21/2019
    Project Initiation Form PRC Submitted 03/28/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Status Advertised 06/29/2024
    Project Management
    100% Design 100% Package Received 01/19/2024
    100% Design 100% Package Comments to DE 02/22/2024
    25% Design 25% Package Received 11/02/2022
    25% Design 25% Package Comments to DE 12/05/2022
    25% Design 25% Package Received - Resub 1 02/21/2023
    25% Design 25% Package Received - Resub 2 05/23/2023
    25% Design Design Public Hearing 08/29/2023
    75% Design 75% Package Received 10/19/2023
    75% Design 75% Package Comments to DE 11/23/2023
    Final Design PS&E Received 03/27/2024
    Final Design PS&E Received - Resub 1 04/22/2024
    Final Design PS&E Received - Resub 2 05/24/2024
    Final Design PS&E Received - Resub 3 08/14/2024