Project Description:
PLYMPTON- BRIDGE REPLACEMENT, P-14-001 (445), WINNETUXET ROAD OVER WINNETUXET RIVER
The intent of the design is to match existing dimensions, and to replace the bridge in-kind with a timber bridge. Widening the bridge and roadway or deviating significantly from existing conditions would result in impacts to wetlands and water, permitting requirements, ROW, and increasing the limits and costs of work.
Location:
  • Town of Plympton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2024
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $2,121,772.30
    Estimated Total Federal Participating Construction Cost: $2,329,645.24
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: PS&E Received - Resub 1 (as of 04/22/2024 )

    Contracts (1) Progress
    # 77845 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: PLYMPTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $989,302.40
    State Cost: $247,325.60
    Total Cost: $1,236,628.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2019
    Project Initiation Form PIF Entered 03/21/2019
    Project Initiation Form PRC Submitted 03/28/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management
    100% Design 100% Package Received 01/19/2024
    100% Design 100% Package Comments to DE 02/22/2024
    25% Design 25% Package Received 11/02/2022
    25% Design 25% Package Comments to DE 12/05/2022
    25% Design 25% Package Received - Resub 1 02/21/2023
    25% Design 25% Package Received - Resub 2 05/23/2023
    25% Design Design Public Hearing 08/29/2023
    75% Design 75% Package Received 10/19/2023
    75% Design 75% Package Comments to DE 11/23/2023
    Final Design PS&E Received 03/27/2024
    Final Design PS&E Received - Resub 1 04/22/2024