Project Description: |
HARWICH- BRIDGE PRESERVATION OF H-10-013, H-10-014 AND H-10-016 ALONG ROUTE 6
The work under this Contract consist of performing bridge structural and substructure work at Bridge H-10-013 (49V) Pleasant Lake Avenue over Route 6, Bridge H-10-014 (4A9) Route 137 Brewster-Chatham Road over Route 6, and Bridge H-10-016 (46T) Route 6 over Depot Street in Harwich.
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Project Manager: | Albin Napit |
Estimated Total Contract Cost: | $2,751,600.00 |
Estimated Total Federal Participating Construction Cost: | $3,001,760.00 |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|