Project Description:
SALEM- PEABODY- BOSTON STREET IMPROVEMENTS
The project limits include a 0.84-mile segment of Boston Street from Howley Street in Peabody to Essex Street in Salem. In addition, the limits of work include a 0.12-mile segment of Essex Street at the intersection of Boston Street, a 0.03-mile segment of Aborn Street approaching Boston Street, a 0.01-mile segment of Pope Street approaching Boston Street, and a 0.01-mile segment of Goodhue Street approaching Boston Street. Major improvements to the corridor include incorporating complete streets design elements such as off-road separated bike lanes for the majority of the corridor (with on-road bike lanes in the short segments where the cross-section is too narrow for separated bike lanes), and ADA/AAB compliant sidewalks, pedestrian ramps, and crosswalks. The proposed cross-section for Boston Street includes one-lane of travel in each direction with additional turn lanes at signalized intersections, where warranted, on-street parking for portions of the corridor, and bicycle facilities on both sides of the roadway. New traffic signals are proposed at the intersections of Boston Street at Aborn Street and Boston Street at Pope Street. The existing traffic signals at the intersections of Main Street and Howley Street, Boston Street and Essex Street, Boston Street and Bridge Street/ Proctor Street/ Goodhue Street, and Boston Street and Grove Street/ Nichols Street will be reconstructed, and the two existing traffic signals at mid-block crossings along the corridor will be removed. Sidewalks along Boston Street will be reconstructed, and the curbs will be shifted along portions of the corridor to narrow the roadway cross-section and to provide off-road bicycle facilities. Landscape strips will be provided between the off-road separated bicycle lanes and the edge of curb for portions of the corridor.
Location:
  • City of Peabody
  • City of Salem
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $20,152,037.80
    Estimated Total Federal Participating Construction Cost: $24,187,705.20
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Received (as of 01/17/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: PEABODY
    SALEM
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $14,172,868 (STBG)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $11,338,294.40
    State Cost: $2,834,573.60
    Total Cost: $14,172,868.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2019
    Project Need Form PNF Approved 03/20/2019
    Project Initiation Form PIF Entered 03/21/2019
    Project Initiation Form PIF Approved 03/21/2019
    Project Initiation Form PRC Submitted 03/22/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management
    25% Design 25% Package Received 08/25/2020
    25% Design 25% Package Comments to DE 12/03/2020
    25% Design 25% Package Received - Resub 2 10/07/2021
    25% Design Design Public Hearing 09/27/2022
    75% Design 75% Package Received 01/17/2024