Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ABINGTON- INTERSECTION IMPROVEMENTS AT HANCOCK STREET AND CHESTNUT STREET
The project includes safety and operational improvements at the Chestnut Street and Hancock Street intersection in Abington where a significant crash history has been experienced. The intersection experiences a crash rate of 1.22 C/MEV over double the state and district average. It also falls within the HSIP Cluster of 2011-2013. After a thorough alternatives analysis, the concept that gained overwhelming support during the Town's public outreach process involves converting the unsignalized intersection to a modern single-lane roundabout. The project is anticipated to extend along Chestnut Street from 300 feet west of Hancock Street to 300 feet east of the intersection, a length of approximately 600 feet. Along Hancock Street, the project is anticipated to extend from 300 feet north of Chestnut Street to 400 feet south of the intersection, a length of approximately 700 feet. A roundabout is anticipated to improve safety and operations and reduce vehicle speeds and conflict points as well as reduce delays and idling time. In addition, the roundabout's splitter islands will result in shorter pedestrian crossing distances and refuge areas for pedestrians to cross one directional lane of traffic at a time. Further, the roundabout will provide additional opportunities for landscaping providing an aesthetically pleasing addition to Abington. Under this scenario, each approach would consist of a single approach lane and single departure lane, separated by a splitter island. Sidewalks are proposed to replace existing sidewalks along the eastern side of both Hancock Street legs, along the southern side of the eastern Chestnut Street leg, and on the northwest corner; pedestrian crossings are anticipated at the eastern and northern legs. Adjustments to the vertical alignment along the southern Hancock Street approach are required to flatten the slope and improve sight lines. Roundabout warning signs are proposed along all approaches to alert drivers of the intersection. Warning signs may be supplemented with yellow flashing beacons to further draw attention to the roundabout. The goal is also reconstructing the existing sidewalk and curb ramp to be ADA/AAB compliant and minor drainage alteration.
Location:
  • Town of Abington
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Stephanie Upson
    Estimated Total Contract Cost: $4,371,392.17
    Estimated Total Federal Participating Construction Cost: $4,798,809.81
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Comments to DE (as of 09/06/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: ABINGTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Project Cost = $4,798,910 - STBG; d) MPO score 41.06; i) Status 25% Design
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,146,172.00
    State Cost: $1,036,543.00
    Total Cost: $5,182,715.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/25/2019
    Project Need Form PNF Approved 02/01/2019
    Project Initiation Form PIF Entered 03/25/2019
    Project Initiation Form PIF Approved 03/06/2019
    Project Initiation Form PRC Submitted 03/26/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management
    25% Design 25% Package Received 05/20/2021
    25% Design 25% Package Comments to DE 09/06/2021