Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTHBRIDGE- INTERSECTION IMPROVEMENTS AT ROUTE 122 (PROVIDENCE ROAD), SCHOOL STREET, SUTTON STREET, AND UPTON STREET
The project involves signalization of the intersection of Route 122 (Providence Road) at School Street, Sutton Street and Upton Street. Additional work includes pavement rehabilitation, sidewalk reconstruction and related work.
Location:
  • Town of Northbridge
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: David Shedd
    Estimated Total Contract Cost: $3,850,200.00
    Estimated Total Federal Participating Construction Cost: $4,135,400.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTHBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $4,466,232, Design Status = Approved, YOE = 8%, PM Score = 16 out of 27
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $4,019,608.80
    State Cost: $446,623.20
    Total Cost: $4,466,232.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/29/2019
    Project Need Form PNF Approved 03/25/2019
    Project Initiation Form PIF Entered 03/29/2019
    Project Initiation Form PIF Approved 03/29/2019
    Project Initiation Form PRC Submitted 04/08/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management