Project Description:
SEEKONK- INTERSECTION IMPROVEMENTS AND RESURFACING ON ROUTE 44 (TAUNTON AVENUE) FROM RI LINE TO PECK STREET INCLUDING ROUTE 114A/FALL RIVER AND ARCADE AVE INTERSECTIONS
Work on this project includes reconstruction of the Route 44/Route 114A and Route 44/Arcade Avenue intersections. New traffic signals with associated geometry is proposed at each intersection. Route 44 will be resurfaced from the Rhode Island State line to Peck Street. Sidewalks will be installed and reconstructed along with the installation of ADA compliant curb ramps. Bicycle accommodation will be improved along the corridor. A culvert at Runnings River will also be replaced.
Location:
  • Town of Seekonk
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $12,005,540.00
    Estimated Total Federal Participating Construction Cost: $14,228,100.03
    District: District 5
    Current Status: 25% Package Comments to DE (as of 04/05/2021 )

    Contracts (2) Progress
    # 115752 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77849 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/01/2019
    Project Need Form PNF Approved 03/29/2019
    Project Initiation Form PIF Entered 04/01/2019
    Project Initiation Form PIF Approved 04/01/2019
    Project Initiation Form PRC Submitted 04/02/2019
    Project Review Committee PRC Approved 04/18/2019
    Project Management
    25% Design 25% Package Received 11/18/2020
    25% Design 25% Package Comments to DE 04/05/2021