Project Description:
DISTRICT 2- ADA RETROFITS AT VARIOUS LOCATIONS
The work to be done under this contract consists of pedestrian ramp construction, sidewalk reconstruction, repairs and upgrades at various pedestrian ramp locations in the following cities and towns; Erving, Greenfield, Hatfield, Monson, Orange, South Hadley, Ware, Whately, and Winchendon. Work shall include, but is not limited to, construction or reconstruction of cement concrete pedestrian ramps, construction or reconstruction of cement concrete and bituminous concrete sidewalks, drainage alterations as needed, removing and resetting of curb and transition curb as required, and repairing of roadway cuts required to perform work.
Location:
Design Responsibility: Consultant
Right of Way Responsibility: MassDOT
Construction Begins: Autumn 2024
Project Manager: Greg Frazier
Estimated Total Contract Cost: $3,668,220.95
Estimated Total Federal Participating Construction Cost: N/A
District: District 2
Current Status: PS&E Received - Resub 2 (as of 01/02/2024 )

Contracts (1) Progress
# 86782 -- Design -- Services
Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2019
    Project Need Form PNF Approved 03/11/2019
    Project Initiation Form PIF Entered 05/07/2019
    Project Initiation Form PIF Approved 03/21/2019
    Project Initiation Form PRC Submitted 10/09/2019
    Project Review Committee PRC Approved 10/15/2019
    Project Management
    100% Design 100% Package Received 05/23/2023
    100% Design 100% Package Comments to DE 06/28/2023
    25% Design 25% Package Received 10/14/2022
    25% Design Design Public Hearing 02/16/2023
    75% Design 75% Package Received 10/14/2022
    75% Design 75% Package Comments to DE 11/21/2022
    Final Design PS&E Received 10/10/2023
    Final Design PS&E Received - Resub 1 12/05/2023
    Final Design PS&E Received - Resub 2 01/02/2024